Estimated time wrong?

says:
Hi Guys,

Is there something wrong with the estimated time?

For example:

Project 1 takes 1 hour
Project 2 takes 1 hour
Estimated time shows 5 hours

Is this done on purpose? and can I switch it off?

Thanks!
Posted at 11:42am on November 26, 2010
says:
I see what happens.

It adds up the tasks for the next day as well.

Is it possible to see the estimated time for a single day only?

Thanks!
Posted 15 years ago
(Remember The Milk) says:
The total time estimated shows the total time for all tasks shown, including future instances of repeating tasks. You may want to create a Smart List that limits tasks to those due today (for example) or use something like sleeper tags to "hide" future repeating tasks.

Hope this helps!
Posted 15 years ago
says:
Thanks Andrewski,

Didn't know this was possible. I've thought of a solution as well.

For example. when I select multiple tasks the program should add up the hours of both tasks. Then there's no need to create a smart list. But perhaps you guys are already working on this.

Thanks for the help!!
Posted 15 years ago
This topic has now been closed automatically due to a lack of responses in the past 90 days.